Weather and delays
Do rain, snow or storms make Swiss public transport late? Every measured arrival, linked to the nearest MeteoSwiss weather station.
When it rains, 1.9 times as many trains arrive late as in dry weather: 13.1% instead of 6.8% of arrivals 3 minutes late or more.
When it rains, public transport arrives measurably later. In rainy hours, 79.9% of arrivals were on time. In dry hours at the same place, the same time of day and the same type of weekday it was 84.2%: a difference of −4.3 points. By mode: Train −6.3 points (late 6.8% → 13.1%), Bus −4.4 points (late 16.8% → 21.1%), Tram −3.2 points (late 13.1% → 16.2%).
Based on 6'457'318 arrivals in rainy hours on 26 weekdays (Monday to Friday; weekends are in section 3). This is an association, not proof: crowds, roadworks or events can play a part. On time: arrival less than 3 minutes after schedule.
- measured arrivals
- 105'913'366
- on time in rain
- 79.9% Monday to Friday
- on time when dry
- 84.2% same place, same hour
- rainy days compared
- 26 of 35 weekdays
01Now and yesterday
Current weather at the 150 automatic MeteoSwiss stations, measured every 10 minutes. Next to it, the latest operating day analysed. Actual-time data only appears the next day.
Weather now
As of 23 Nov, 21:50
- stations with rain in the last hour
- 43 / 150
- of which probably snow (≤ 1 °C)
- 25
- strongest gust (1 h)
- 55 km/hSimplon-Dorf
- Temperature
- -14.0 … 7.4 °C
Dot size: rain in the last hour. Grey: dry.
Latest day analysed: Sunday, 22 November
- All modes: 91.5% on time (typical Sunday: 91.7%)
- Train: 95.2% on time (typical Sunday: 96.1%)
- Bus: 91.0% on time (typical Sunday: 91.0%)
- Tram: 92.2% on time (typical Sunday: 92.2%)
Rain for 70% of arrivals, snowfall for 2.6%, storm gusts for 0.2%; 4.7 °C on average.
Colour: share of on-time arrivals around the station (red = lower). Dot size: rain that day.
02What each kind of weather does
Difference in the share of on-time arrivals, all modes. Always compared with hours without that weather at the same station, the same hour, the same type of weekday and the same calendar week. As a week has only one Saturday and one Sunday, this comparison only works Monday to Friday. Negative means less punctual.
Rain
at least 0.5 mm in the hour, compared with dry hours. 79.9% instead of 84.2% on time · 6'457'318 arrivals on 26 days
Snowfall
precipitation at 1 °C or colder, compared with dry hours. 85.0% instead of 88.6% on time · 11'292 arrivals on 14 days
Snow on the ground
at least 5 cm of snow at the station, compared with snow-free hours. 89.7% instead of 88.4% on time · 22'175 arrivals on 23 days
Storm gusts
gusts of 61 km/h or more, compared with hours below 36 km/h. 83.4% instead of 85.5% on time · 386'169 arrivals on 21 days
Frost
-2 °C or colder, compared with hours of 3 °C or more. 88.9% instead of 89.6% on time · 38'264 arrivals on 21 days
Heat
at least 28 °C, compared with hours between 15 and 25 °C. No hour reached 28 °C in the period. Heat becomes measurable from early summer.
03Rain by mode
Dot: estimated difference in percentage points. Line: 95% interval from 200 bootstrap replicates over operating days. If the line crosses zero, the difference is not established.
- All modes: Average delay in rain 2:04 min, otherwise 1:43 min; cancelled stops 0.85% instead of 0.66%.
- Train: Average delay in rain 1:30 min, otherwise 1:03 min; cancelled stops 2.01% instead of 1.91%.
- Bus: Average delay in rain 2:09 min, otherwise 1:47 min; cancelled stops 0.57% instead of 0.42%.
- Tram: Average delay in rain 1:45 min, otherwise 1:30 min; cancelled stops 2.50% instead of 1.92%.
Weekdays and weekends
Rain effect by day type, all modes. Here without the week match (station, hour and day type only), so that Saturdays and Sundays become comparable. That is why the weekday value differs slightly from above.
04The harder it rains
Difference from dry hours by rainfall in the hour (drizzle 0.1–0.4 mm, light 0.5–1.9, moderate 2–4.9, heavy 5 mm or more). Empty cells: too few days.
05Rain through the day
Difference from dry hours by hour of planned arrival. Only hours with at least 2'000 arrivals in rain. Individual hours vary a lot.
- Train
- Bus
- Tram
TrainBusTram
06Which lines rain hits
Each line compared with itself: the same line at the same stops, the same hour and week, once in rain and once dry. Only lines with at least 200 arrivals in rain on at least 5 days.
For 362 of 1'762 lines the whole 95% interval is below zero. By pure chance about 44 would be expected. Some lines in the lists may therefore be there by chance. The lists only show lines with rain on at least 8 days.
Most sensitive
Bus 859 (ZH)
PostAuto AG · 48.4% instead of 72.6% on time · 345 arrivals, 8 days
Train R91 (VS)
Regionalps · 81.7% instead of 93.9% on time · 2'854 arrivals, 13 days
Train S35 (ZH)
THURBO · 81.6% instead of 94.1% on time · 705 arrivals, 13 days
Bus 973 (ZH)
Verkehrsbetriebe Zürichsee und Oberland · 74.0% instead of 91.6% on time · 880 arrivals, 10 days
Train S11 (ZH)
Schweizerische Bundesbahnen SBB · 81.0% instead of 94.3% on time · 2'788 arrivals, 15 days
Bus 11 (GE)
Transports Publics Genevois · 52.5% instead of 70.3% on time · 18'449 arrivals, 13 days
Bus 735 (ZH)
Verkehrsbetriebe Glattal · 67.9% instead of 85.0% on time · 1'705 arrivals, 12 days
Train S3 (ZH)
Schweizerische Bundesbahnen SBB · 77.5% instead of 94.4% on time · 1'105 arrivals, 13 days
Bus 302 (SG)
Bus Ostschweiz · 79.4% instead of 91.6% on time · 880 arrivals, 9 days
Bus 9 (GE)
Transports Publics Genevois · 63.7% instead of 74.8% on time · 20'234 arrivals, 13 days
Most weatherproof (interval close around zero)
Bus 22 (SO)
Busbetrieb Grenchen und Umgebung · 97.3% instead of 97.4% on time · 4'490 arrivals, 10 days
Bus 5 (BE)
STI Bus AG · 96.3% instead of 95.6% on time · 5'938 arrivals, 10 days
Bus 210 (VD)
Transports publics Vevey-Montreux-Chillon-Villeneuve · 99.4% instead of 98.9% on time · 1'592 arrivals, 9 days
Bus 871 (BE)
Autobusbetrieb RBS · 96.7% instead of 96.1% on time · 1'229 arrivals, 11 days
Tram 20 (ZH)
Aargau Verkehr AG · 95.7% instead of 95.5% on time · 10'777 arrivals, 15 days
Bus 12 (FR)
Service d'automobiles TPF · 97.1% instead of 96.8% on time · 1'801 arrivals, 12 days
Bus 145 (ZH)
Automobildienst SZU · 97.2% instead of 97.7% on time · 2'203 arrivals, 12 days
Train RR20 (VD)
Lausanne-Echallens-Bercher · 97.4% instead of 98.3% on time · 6'066 arrivals, 14 days
Bus 433 (VS)
Sierre-Montana-Crans · 100.0% instead of 98.8% on time · 1'038 arrivals, 9 days
Bus 1 (BE)
STI Bus AG · 95.2% instead of 96.0% on time · 14'525 arrivals, 10 days
All lines analysed
Loading data …
By operator
The same comparison per operator (at least 1,000 arrivals in rain on at least 5 days).
| Schweizerische Bundesbahnen SBB | 150'387 | 25 | 82.6% | 92.4% | −9.7 | −14.8 | −6.5 |
| Regionalps | 3'534 | 13 | 83.3% | 93.0% | −9.7 | −13.1 | −5.3 |
| Transports Publics Genevois | 719'358 | 13 | 71.5% | 79.5% | −8.0 | −11.0 | −3.7 |
| Aargau Verkehr AG | 7'242 | 15 | 83.6% | 91.4% | −7.8 | −13.9 | −4.0 |
| Aargau Verkehr AG | 2'082 | 11 | 78.3% | 86.0% | −7.7 | −22.0 | +2.6 |
| Appenzeller Bahnen (ab) | 12'757 | 18 | 82.3% | 90.1% | −7.7 | −13.4 | −1.5 |
| Verkehrsbetriebe Glattal | 130'186 | 15 | 81.9% | 89.3% | −7.4 | −10.8 | −2.6 |
| THURBO | 31'936 | 18 | 87.7% | 94.8% | −7.1 | −9.3 | −4.3 |
| Busbetrieb Aarau | 39'457 | 10 | 73.3% | 80.0% | −6.8 | −11.9 | +0.4 |
| Transports Publics de la Région Lausannoise sa | 379'927 | 16 | 73.0% | 79.6% | −6.6 | −11.4 | −1.8 |
| Theytaz Excursions Sion | 1'690 | 10 | 72.4% | 79.1% | −6.6 | −16.7 | +0.2 |
| Verkehrsbetriebe Schaffhausen | 18'675 | 14 | 80.3% | 86.7% | −6.5 | −10.4 | −1.3 |
| Autoverkehr RhB | 1'820 | 10 | 72.2% | 78.6% | −6.4 | −14.2 | +4.2 |
| Verkehrsbetriebe Zürich | 354'045 | 15 | 78.5% | 84.8% | −6.4 | −11.1 | −1.3 |
| Service d'automobiles TRN (rvt Auto) | 1'540 | 10 | 77.9% | 84.2% | −6.3 | −11.3 | +2.3 |
| Autobusbetrieb RBS | 38'709 | 16 | 77.5% | 83.6% | −6.0 | −9.6 | −2.7 |
| Automobil Rottal AG | 15'788 | 14 | 71.4% | 77.2% | −5.8 | −12.9 | +0.1 |
| Verkehrsbetriebe Kreuzlingen | 9'433 | 12 | 81.7% | 87.3% | −5.5 | −10.3 | +2.6 |
| Bamert Bus | 3'637 | 11 | 86.4% | 91.9% | −5.5 | −8.6 | −1.5 |
| Trasporti Pubblici Luganesi SA | 85'787 | 9 | 64.1% | 69.6% | −5.5 | −12.6 | +0.8 |
| Verkehrsbetriebe Luzern AG | 141'994 | 14 | 71.3% | 76.6% | −5.3 | −11.9 | +1.4 |
| Stadtbus Frauenfeld | 19'748 | 13 | 83.1% | 88.3% | −5.2 | −9.6 | −1.9 |
| Bus Nyon-Prangins | 14'178 | 14 | 76.3% | 81.4% | −5.1 | −9.2 | −0.6 |
| Stadtbus Winterthur | 142'204 | 13 | 84.6% | 89.7% | −5.1 | −8.9 | −0.9 |
| Transports Publics Neuchâtelois SA (tn) | 48'342 | 11 | 66.0% | 70.9% | −4.9 | −13.5 | −1.7 |
07Where rain matters most
Difference in rain around each weather station (all modes, at least 4 rainy days). Red: less punctual in rain, green: more punctual. Large dots: many arrivals.
| Trient | VS | 87 | 4 | 39.1% | 56.3% | −17.2 | −38.6 | +5.7 |
| Les Marécottes | VS | 717 | 10 | 60.8% | 74.3% | −13.5 | −23.6 | −4.3 |
| Rempen | SZ | 552 | 10 | 59.4% | 70.3% | −10.8 | −20.3 | +0.3 |
| Pully | VD | 93'108 | 15 | 70.2% | 79.6% | −9.4 | −15.6 | −4.0 |
| Tschiertschen | GR | 1'685 | 9 | 59.8% | 69.1% | −9.3 | −25.3 | +2.6 |
| La Dôle | VD | 355 | 7 | 75.8% | 84.0% | −8.3 | −17.1 | +1.0 |
| Blatten, Lötschental | VS | 465 | 9 | 66.2% | 74.5% | −8.3 | −18.7 | +5.5 |
| Martina | GR | 1'400 | 10 | 70.6% | 78.8% | −8.3 | −16.2 | −2.6 |
| Martigny | VS | 7'850 | 13 | 74.6% | 82.6% | −8.0 | −13.7 | −1.0 |
| Genève / Cointrin | GE | 732'398 | 15 | 71.8% | 79.7% | −7.9 | −11.0 | −4.3 |
08Day by day
Top: punctuality of all arrivals against a typical day of the same type (median of the period’s weekdays, Saturdays or Sundays). Bottom: share of arrivals that fell in a rainy hour.
Across 50 days: correlation between rain share and punctuality deviation, trains r = −0.68, buses r = −0.30, all r = −0.35. Negative means: the wetter the day, the less punctual.
The least punctual days and their weather
Only 1 of the five least punctual days were nearly dry: the bad days are also the wet ones.
Thursday, 12 November
78.0% on time, −6.0 points against a typical weekday · rain for 51% of arrivals · 10.0 °C
Thursday, 19 November
80.2% on time, −3.9 points against a typical weekday · rain for 36% of arrivals · 8.6 °C · snowfall 0.5% · storm gusts 7.9%
Wednesday, 11 November
81.4% on time, −2.6 points against a typical weekday · rain for 18% of arrivals · 11.5 °C
Tuesday, 27 October
81.7% on time, −2.3 points against a typical weekday · rain for 0% of arrivals · 11.1 °C
Tuesday, 17 November
81.7% on time, −2.3 points against a typical weekday · rain for 25% of arrivals · 11.5 °C · storm gusts 11.4%
09What the numbers say and what they don’t
Association, not cause. When it rains, more people take public transport, roads are busier, and other things happen on rainy days too. Comparing the same place, hour and week removes much of that, but not all of it.
Uncertainty comes from days, not arrivals. There are millions of arrivals but only 26 rainy days in the comparisons. A single disrupted day can move a number, so we show intervals from a bootstrap over whole operating days.
The seasons are still missing. The data runs from 4 Oct 2026 to 22 Nov 2026. There is no heat in it yet. Frost, snow and heat each occur in one season only. Comparing within the same week softens such seasonal effects but does not remove them. New data arrives every day.
Without the week match (station, hour and weekday type only) the rain effect is −3.3 points across 10'771'953 arrivals. The stricter within-week comparison is shown above.